Buckley Court - London

Client: Axis

Location: Buckley Court, London

System Used: Nimbus Waterproofing System

Date Completed: 2026

Overview

Buckley Court is a seven-storey residential apartment building in South London that required a full refurbishment of its failing flat roof waterproofing system. The project involved carefully removing the existing green roof and solar PV panels before installing a new Nimbus waterproofing system to improve long-term performance. Both were reinstated following completion of the roofing works, with residents remaining safely in occupation throughout.

The Challenge

The existing single-ply roof had developed multiple defects, resulting in persistent water ingress. Faulty drainage and a defective AOV also contributed to ongoing issues. Restricted roof access, poor weather and the need to carefully remove and reinstate the existing green roof and solar PV panels added further complexity to the project.

Our Solution

The existing roof was stripped back to the concrete deck before a new Nimbus waterproofing system with tapered insulation laid to improved falls was installed. New rainwater outlets and a replacement AOV were fitted to improve drainage and reduce future water ingress, before the green roof was carefully reinstated. Close communication with the client and weekend working helped minimise programme delays caused by poor weather.

The Results

  • Approximately 290m² of new Nimbus waterproofing installed

  • Existing green roof successfully reinstated

  • Improved roof drainage with new rainwater outlets

  • New AOV installed to reduce future water ingress

  • Manufacturer-approved installation with a new warranty

  • Residents remained safely in occupation throughout the eight-week project